administrators Reply Quote

Answer : Explanation : I. InputsEnterprise environmental factorsOrganizational process assetsActivity listActivity attributesResource availabilityProject management planII. Tools and TechniquesExpert JudgmentAlternatives analysisPublished estimating dataProject management softwareBottom-up estimatingIII. OutputsActivity resource requirementsActivity atributes (updates)Resource breakdown structureResource calendars (updates)Requested changes