administrators Reply Quote

Answer : 1 Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution Explanation : Answer: A) Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution Explanation: Answer B defines the timing that should be addressed in the risk management plan. Answer C defines the methodology that should be identified in a risk management plan. Answer D touches on the budgeting and tracking that should be defined in the risk management plan.