Answer : 2 Use the cost of similar projects Explanation : Answer: B) Use the cost of similar projects Explanation: Although it is less accurate than adding up individual costs from the WBS, it is less time consuming. The trade-off is accuracy. Answer A is incorrect because to do a more accurate cost estimate, you need to delve into details. Answer C is tempting also, and possible, except we don