administrators Reply Quote

Answer : Explanation : I. InputsOrganizational process assetsProcurement management planEvaluation criteriaProcurement document packageProposalsQualified sellers listProject management plan                 - Risk register                 - Risk related contractual agreementsII. Tools and TechniquesWeighting systemIndependent estimatesScreening systemContract negotiationSeller rating systemsExpert judgmentProposal evaluation techniquesIII. OutputsSelected sellersContractContract management planResource availabilityProcurement management plan (updates)Requested changes