Answer : Explanation : I. InputsSchedule management planSchedule baselinePerformance reportsApproved change requestsII. Tools and TechniquesProgress reportingSchedule change control systemPerformance measurementProject management softwareVariance analysisSchedule comparision bar chartsIII. OutputsSchedule model data (updates)Schedule baseline (updates)Performance measurementsRequested changesRecommended corrective actionsOrganizational process assets (updates)Activity list (updates)Activity attributes (updates)Project management plan (updates)