administrators Reply Quote

Answer : Explanation : I. InputsCost baselineProject funding requirementsperformance reportsWork performance informationApproved change requestsProject management planII. Tools and TechniquesCost change control systemPerformance measurement analysisForecastingProject performance reviewsProject management software Variance managementIII. OutputsCost estimate (updates)Cost baseline (updates)Performance measurementsForecasted completionRequested changesRecommended corrective actionsOrganizational process assets (updates)Project management plan (updates)