Answer : Explanation : I. InputsProject scope statementWork breakdown structureWBS dictionaryProject scope management planPerformance reportsApproved change requestsWork performance informationII. Tools and TechniquesChange control systemVariance analysisReplanningConfiguration management systemIII. OutputsProject scope statement(updates)Work breakdown structure(updates)WBS dictionary (updates)Scope baseline (updates)Requested changesRecommended  corrective actionOrganizational process assets (updates)Project management plan (updates)