Answer : Explanation : I. InputsEnterprise environmental factorsOrganizational process assetsProject scope statementActivity listActivity attributesActivity resource requirementsResource calendarsProject management plan               - Risk register               - Activity cost estimatesII. Tools and TechniquesExpert judgmentAnalogous  estimatingParametric estimatingThree-point estimates Reserve analysisIII. OutputsActivity duration estimatesActivity attributes (updates)